8.01.16 Expiration of Approvals
Unofficial copy. It may be out of date. Not legal or zoning advice. Zoning rules change, and only the city or county can say for sure what is allowed on a property. Confirm with the city or county planning department before you buy, sign or build.
The official Daniel code is at https://danielutah.gov/code-and-ordinances/.
Text pulled 2026-10-19 from this source.
Title 8 only; a separate 2025 subdivision amendment ordinance is not merged in.
Tables (like use tables) may not copy cleanly, so check any table against the official code.
Confirm anything here with Daniel planning before you rely on it.
(1) Building Permits. A building permit shall expire if construction is not begun within one hundred eighty (180) days from the date the building permit was issued. A building permit shall expire if construction is not completed and a Certificate of Occupancy and Land Use Compliance obtained within two (2) years from the date the building permit was issued. The building official may, for good cause shown, extend the expiration date for a period of time not to exceed one (1) additional year.
(2) Administrative Approvals. The planning commission may delegate to the planning staff or development review committee specific authority to act on certain administrative matters. In the event that the development is one of the types of development where authority has been so delegated, any approvals granted by the planning staff or development review committee shall expire
one hundred and eighty (180) days after such approval is given. The approving body may grant one extension of up to ninety (90) additional days on a finding of good cause by the approving body.
(3) Preliminary Approvals of Developments. Preliminary approvals of developments shall expire if application for final approval has not been submitted for consideration within one (1) year from the date of receiving preliminary approval. An extension not to exceed one (1) additional year upon a finding of good cause.
(4) Final Development Approvals. Final approval of developments shall expire if the plat is not recorded within one (1) year from the date of receipt of final approval by the planning commission. The planning commission may grant a one (1) year extension upon a showing of good cause.