02.0924 Review and Approvals
Unofficial copy. It may be out of date. Not legal or zoning advice. Zoning rules change, and only the city or county can say for sure what is allowed on a property. Confirm with the city or county planning department before you buy, sign or build.
The official Elmo code is at https://emery.utah.gov/wp-content/uploads/2024/01/ZONING-ORDINANCES.pdf.
Text pulled 2026-10-19 from this source.
This is the town's 1975 typed zoning ordinance, the only one posted online (on Emery County's site). It may be outdated; confirm the current rules with the town.
Tables (like use tables) may not copy cleanly, so check any table against the official code.
Confirm anything here with Elmo planning before you rely on it.
The Planning Commission shall review the plan to determine its compliance with the portion of
the master plan that shall have been adopted by the Planning Commission. In considering
approval of the development, the Planning Commission shall, among other things, make sure that
such development will mesh harmoniously with the surrounding area, that it will not produce a
volume of traffic beyond the capacity of the surrounding street system, that requirements for
utilities, off-street parking, traffic circulation and other public requirements will be adequately
met and that the standards and intent of this section shall be adequately complied with.
The Planning Commission may require changes to be made in the plan. They may also require
additional yards and buffers or other improvements to be installed along with greater amounts of
landscaping or parking spaces. Said changes may be imposed as conditions of approval w here it
is determined by the Planning Commission that such are necessary to insure that the
development will mix harmoniously with adjoining or nearby uses.
An application for approval of a recreation vehicle court shall be granted or denied only after a
public hearing by the Planning Commission. Notice of the hearing shall be given at least five (5)
days prior to said hearing. If approved by the Planning Commission, the application, with the
Planning Commission’s recommendations, shall be submitted to the city council for its approval.
An application denied by the Planning Commission may be appealed to the city council ten (10)
days after the denial is made by the Planning Commission. Approval of the preliminary plan
shall be valid for a period of one (1) year.
02.0922 Approval of Plans and Documents Necessary · 02.0925 Final Site Plan