11.02.04 Phasing
Unofficial copy. It may be out of date. Not legal or zoning advice. Zoning rules change, and only the city or county can say for sure what is allowed on a property. Confirm with the city or county planning department before you buy, sign or build.
The official Fruit Heights code is at https://www.fruitheights.gov/201/Municipal-Code.
Text pulled 2026-10-19 from this source.
Partial copy: about 20 chapters (most zone and administration chapters, ch. 1-7, 8A-8C, 8E, 9A-9B, 10B, 12-15, 19-20) are scanned images on the city's site and are not included. Use the official code for those.
Tables (like use tables) may not copy cleanly, so check any table against the official code.
Confirm anything here with Fruit Heights planning before you rely on it.
Subdivisions may be done in phases. Each phase shall follow the Approval Procedure as outlined in 11.02.03.
1. The Preliminary Plat shall include all ground anticipated to be subdivided. The phases shall be shown as part of the Preliminary Plat and submitted with the Preliminary Plat.
2. Development shall be organized such that the phases will be contiguous, and the required improvements and infrastructure will be continuous as deemed feasible and desirable by the Administrative Land Use Authority.
3. Less desirable or expensive aspects of the Subdivision should not be delayed to the final phases of development.
4. The Administrative Land Use Authority may require a pro-rated portion of the improvements and infrastructure be developed, or guaranteed in escrow, in earlier phases.
5. Where it is prudent to install improvements and infrastructure that extend into the next phase, such work may be done when it is shown on the plans and approved accordingly.