A. An applicant for an open pit excavation permit shall provide the site plan required by Section 14-24-020(C)(3) to the City seven days prior to the scheduled review with the Development Review Committee. The Development Review Committee will review the application using the following criteria:
1. That the proposed use will not disrupt the development character of the adjacent properties.
2. That the proposed site is adequate in size and shape to accommodate the intended use, and that all requirements for the zoning district, including but not limited to: setbacks, walls, landscaping and buffer yards are met.
3. That the proposed site has adequate access to public streets to carry the type and quantity of traffic which may be generated by the use.
4. All appropriate conditions are met and other conditions to protect the health, safety, and welfare of the residents are addressed.
B. The Planning and Zoning Commission will review the recommendation of the DRC. The Planning and Zoning Commission shall act as the land use authority and may grant the permit, insuring the conditions required by this chapter are met, and adding such additional conditions as necessary to protect the health, safety, and welfare of the resident of the City.
C. Each conditional use permit granted will be reviewed by-annually by the Development Review Committee to determine compliance with the conditions imposed by the Planning and Zoning Commission. The City Public Works Director may schedule an earlier review if he/she observes a violation of any condition.
D. Expenses incurred by the City, in determining non-compliance with conditions, must be reimbursed to the City by the permitee prior to reinstating the permit.