Saratoga Springs zoning code

19.14.09 Failure to Begin and Complete Development

Unofficial copy. It may be out of date. Not legal or zoning advice. Zoning rules change, and only the city or county can say for sure what is allowed on a property. Confirm with the city or county planning department before you buy, sign or build. The official Saratoga Springs code is at https://www.saratogasprings-ut.gov/202/Land-Development-Code. Text pulled 2026-10-19 from this source. The city's use tables are images in its PDFs, so they appear nearly empty here. Check the official code for any use table. Tables (like use tables) may not copy cleanly, so check any table against the official code. Confirm anything here with Saratoga Springs planning before you rely on it.
If no substantial construction (as defined in the applicable building code) has occurred in a development that has been granted Site Plan approval pursuant to this Chapter within twentyfour months from the date of approval, the Planning Director shall revoke Site Plan approval. 1. The Land Use Authority may grant extensions of time when such extensions will promote public health, safety, and general welfare. Said extension must be requested within twenty-four months of Site Plan approval and shall not exceed twenty-four months. 2. For developments that are subject to a development or bond agreement, and if the development or bond agreement establishes the deadline for commencement of substantial construction, the provisions of the development or bond agreement shall apply.

19.14.08 Issuance of a Certificate of Occupancy · 19.15.01 Purpose

Ask a broker about Saratoga Springs zoning, free

CallTextFree summary