17.26.040 APPLICATION REQUIREMENTS
Unofficial copy. It may be out of date. Not legal or zoning advice. Zoning rules change, and only the city or county can say for sure what is allowed on a property. Confirm with the city or county planning department before you buy, sign or build.
The official Millville code is at https://millvilleut.gov/city-government/citycode/.
Text pulled 2026-10-19 from this source.
Tables (like use tables) may not copy cleanly, so check any table against the official code.
Confirm anything here with Millville planning before you rely on it.
All applications to the planning commission for development in the commercial general zone shall be accompanied by the following technical information reports, all prepared by a licensed engineer or landscape architect, as the case may be, in sufficient detail to allow evaluation of health, safety, and general public welfare aspects of the development. The reports shall include:
A. Site Development Plans:
1. A grading or earthmoving plan showing existing and proposed contours of the property. The contour lines shall extend to at least one hundred feet (100') outside the property lines, or a sufficient distance to show on site and off site drainage channels. The contour interval shall be two feet (2').
2. Detailed site plans and elevation drawings showing the location of all existing and proposed streets, easements, and drainage channels.
3. Traffic flow study, if deemed necessary by the city engineer.
4. Detailed site plan showing the location and proposed connection points of utilities, including, but not limited to, water, natural gas, electricity, sewer and telecommunications.
5. A fire protection plan accompanied by letters of approval from the fire chief and the county fire marshal.
6. Detailed site plan showing the boundaries of any established FEMA or any other floodplain within the property and within six hundred feet (600') of the property lines.
7. When any area of the lot exceeds slope class 1 specifications, a hillside development permit shall be required with the application.
B. Drainage Control Plans: A drainage control plan and report based upon the following criteria:
1. Independent Drainage Systems: All drainage systems shall be independent from the sanitary sewer or septic system.
2. Natural Drainage Channel: No natural drainage channel shall be filled, obstructed, or diverted, nor shall the point of entrance and exit from the property be changed without the approval of the city engineer.
3. Drainage Basin Upstream: All of the drainage basin upstream of the development shall be considered in the analysis as fully developed and considered in the design of any stormwater drainage facilities.
4. Effects On Downstream Property: The effects on the downstream property owners relative to increased flood potential shall also be considered in the design, including acquisition of easements, construction or modification of improvements where needed.
5. Existing Drainage Channels: Developments shall use existing drainage channels or newly constructed control structures and retention facilities to control its stormwater runoff so that no net increase in storm runoff will occur on the downstream properties.
6. Stormwater Adequately Conveyed: The stormwater from a 50-year frequency storm with a duration equal to the time of concentration shall be adequately conveyed within the storm drainage channels, from the project to established drainage outlet channels without creating flood hazards to adjoining properties.
7. Underground Pipe System: When an underground pipe system is required, it shall be designed to carry a 10-year storm. The minimum storm drain size shall be twelve inches (12").
8. Cross Gutter Drains: Cross gutter drains on streets shall be avoided where possible. They shall not be allowed on major streets.
9. Groundwater Sources On Property: When springs or other groundwater sources are found on the property, development plans must be reviewed and approved by Bear River health department or appropriate government agency.
10. Constructed Outside Floodplain: All buildings shall be constructed outside the limits of any of the 100-year floodplain. Foundations within five hundred feet (500') of the floodplain boundary shall be a minimum of eighteen inches (18") above the 100-year flood stage, except on floodplains subject to FEMA regulations, in which case they shall be a minimum of two feet (2') above the 100-year flood stage.
11. Stormwater Permits: Discharge permits are required from most industries that discharge stormwater runoff to surface waters such as lakes or streams.
Stormwater pollution prevention plans must be in place prior to application. All construction activities that disturb more than five (5) acres (clearing, grading and excavating) are required to obtain a UPDES construction stormwater permit (mainly for sediment and erosion control).
C. Geology Soils Report: A geology soils report shall contain at least the following information:
1. A foundation investigation including bearing strength capacity, sheer strength, and shrink/swell potential of soils and conclusions and recommendations on the effects of soil conditions on foundation and structural stability.
2. Location and yield of seeps and springs;
3. A description of geological structural features, including any geological limitations;
4. Conclusions and recommendations regarding the effect of geologic conditions on the proposed development, together with recommendations identifying the means proposed to minimize any hazard to life or property or adverse impact on the natural environment.
D. A Landscape Plan: The plan shall be of adequate scale and detail to indicate general grading and plantings along irrigation and temporary erosion control. For areas to be used as surface retention basins for stormwater runoff, the plan shall identify the location and sizing of control facilities and address operation and maintenance of the control facility in conjunction with the landscape improvements.
E. Additional Information: Other reports, plans, and information as may be deemed necessary by the planning commission, city council, or city engineer may be requested as a condition to the application procedure. (Ord. 2020-1, 2020: Ord. 2013-2, 2013: Ord. 2012-4, 2012)
17.26.030 CONDITIONAL USES · 17.26.050 AREA, SETBACK AND HEIGHT REQUIREMENTS